Mary McLeod Bethune School

3301 Old York Rd, 19140

Grades: PreK-8

Active Project (s): Playground Improvements; Major Interior Renovation; Energy Conservation Improvements

Major Renovations (Phase III): Refinish all classrooms, corridors, and ancillary spaces; Upgrade IT; Create accessible toilet rooms; Upgrade electrical service and distribution; Replace all roofs; Replace all windows; Refurbish exterior masonry

Budget:  $11,001,648

Status: Pending Bid Process

The Trust for Public Land logo

TPL Playground Improvement

Budget:  $969,510

BOE Approval Date: TBD

Status: Design Phase

The GESA program will focus on the following Energy Conservation Measures (ECMs): LED light fixtures and controls: Installation of high-efficiency LED lighting fixtures to both the interior and exterior; Automatic Temperature Controls (ATC) upgrades and repairs to allow improved comfort; levels and reduce energy consumption.; New boilers and chillers to improve cooling and new terminal units for heating and ventilation.; Steam to hot water heating conversions; New Air Handling Units (AHUs) for improved heating and ventilation.; Electrical System upgrades as needed; seal the envelope of buildings to reduce heat loss

Budget: $4,487,387

Board Approval Date: May 27, 2022

Status: Construction Phase

Construction Phase 90%