William L. Sayre High School

5800 Walnut St, 19139

Grades: 9-12

Active Project (s): Major HVAC Replacements

 

Major HVAC Replacement of boilers, boiler room equipment, and oil tanks, powering off all and adding additional means of egress from the boiler room. Install steam traps in classrooms.

Budget: $4,002,000

BOE Approval Date: May 28, 2020

Project Complete August 2024

Progress

Construction Phase 98%