Guaranteed Energy Savings Act (GESA) Project at Conwell

School: Russell Conwell Middle School

Construction Budget: $12,565,293

 

Major mechanical upgrade to include new piping, pumps, boiler and chiller to provide heat and air conditioning. The goal of the project is to use energy efficient systems and reduce the energy used to heat and cool the building.

Design Project Manager: Jerry Lamina
Construction Project Manager: George Leone
Project Inspector: Patrick McMahon

General Contractor: Johnson Control Inc.

New boiler delivery.
New chiller delivery.
New opening for upgraded cooling tower piping.

NOVEMBER 19, 2019

Project Start

651 DAYS

Project Duration

AUGUST 31, 2021

Project Completion

$12,565,293

Project Budget

Progress

Construction Progress: 61%

Russell Conwell Middle School

Environmental Results

There are no environmental testing results at this time.