Edwin Forrest School

 

7300 Cottage St, 19136

Grades: K-5

Active Project (s): Major Renovation

Renovation of classrooms, new lights and electric upgrades, Mechanical and Plumbing upgrades, New Kitchen, roof, paved yard, and Asbestos abatement.

General Contract Budget: $11,590,000
Mechanical Contract Budget: $5,295,000
Plumbing Contract Budget: $1,040,000
Electrical Contract Budget: $4,343,226

BOE Approval  Date: 6/23/22

Progress

Construction Phase 95%

Community Meetings Recordings

Apr 28, 2022  Click Here
May 18, 2022 Click Here 
August 3,2022 Click Here

Community Meetings Schedule

August 3rd (Virtual)
August 11th (In-Person) The Little School House

Recently Completed

Fire Alarm Replacement

Budget: $198,000

BOE Approval Date: $ 4/26/218

Scope of Work: Complete replacement and ADA Upgrade of Fire alarm System