Science Lab Renovation at GAMP

School: Girard Academic Music Program

Construction Budget: $1,054,500

 

The work at GAMP is focused on upgrades to two existing science labs and one shared prep room on the third floor of the original building. These spaces will receive new tables, casework, ceiling, lighting, shades, display boards, and additional electric and data outlets.

Design Firm: Princeton Engineering Services
Design Project Manager: Nicole Ward
Construction Project Manager: George Leone
Project Inspector: Rich Lepore

General Contractor: TE Construction Services, LLC
Mechanical Contractor: GEM Mechanical Services, Inc.
Electrical Contractor: Hyde Electric Corporation
Plumbing Contractor: Five Star, Inc.

JULY 18, 2019

Project Start

323 DAYS

Project Duration

JUNE 5, 2020

Project Completion

$1,054,500

Project Budget

Progress

Construction Progress: 42%