School: Girard Academic Music Program
Construction Budget: $1,054,500
On March 28th, the Board will hold an Action Meeting at 4 p.m, followed immediately by the Intermediate Unit Meeting. Find materials here.
Design Firm: Princeton Engineering Services
Design Project Manager: Nicole Ward
Construction Project Manager: George Leone
Project Inspector: Rich Lepore
General Contractor: TE Construction Services, LLC
Mechanical Contractor: GEM Mechanical Services, Inc.
Electrical Contractor: Hyde Electric Corporation
Plumbing Contractor: Five Star, Inc.
JULY 18, 2019
Project Start
323 DAYS
Project Duration
JUNE 5, 2020
Project Completion
$1,054,500
Project Budget
There are no environmental testing results at this time.