Roof Replacement at Greenfield

 

 

School: Albert Greenfield Elementary School

Construction Budget: $1,266,856

 

Replacement of the existing roof including all demolition of existing roof, new roofing material, new drains, concrete deck repair if necessary.

Design Project Manager: Ken Rux
Construction Project Manager: Frank Ratka III
Project Inspector: Robert Baldwin

General Contractor: Weatherproofing Technologies, Inc.

New finished roof.

New solar panels.

New finished roof.

JUNE 8, 2020

Project Start

387 DAYS

Project Duration

JUNE 31, 2021

Project Completion

$1,266,856

Construction Budget

Progress

Construction Progress: 99%