School: The Haverford Center: Bright Futures
Construction Budget: $771,202
Design Project Manager: Nicole Ward
Construction Project Manager: Kevin Courtney
Project Inspector: Trever Alfonso
Design Firm: Waterproofing Technologies Inc.
General Contractor: United States Roofing Corporation
Ariel view of the roof.
DECEMBER 31, 2019
Project Start
137 DAYS
Project Duration
MAY 14, 2020
Project Completion
$771,202
Construction Budget