John B. Kelly

 

School: John B. Kelly Elementary School

Construction Budget: $2,669,000

22 classrooms will be fully abated and modernized with completely new finishes including floors, paint, ceilings, doors, and hardware. Electrical improvements will include new lights and receptacles. Building will also undergo full paint and plaster stabilization and lead-safe certification.

Design Project Manager: Gamil Hall
Construction Project Manager: Mario Tamborello
Project Inspector: Gino Berardinucci

Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: The Bedwell Company
Electrical Contractor: McGoldrick Electric

MAY 16, 2020

Project Start

229 DAYS

Project Duration

DECEMBER 31, 2020

Project Completion

$2,669,000

Construction Budget

Progress

Construction Progress: 100%

JB Kelly Elementary

Environmental Results

There are no environmental testing results at this time.