Grover Washington Middle School

201 E Olney Ave,19120

Grades: 5-8

Active Project (s): Energy Performance Improvements; Storm Water Management System Installation

The GESA program will focus on the following Energy Conservation Measures (ECMs): LED light fixtures and controls: Installation of high-efficiency LED lighting fixtures to both the interior and exterior; Automatic Temperature Controls (ATC) upgrades and repairs to allow improved comfort; levels and reduce energy consumption.; New boilers and chillers to improve cooling and new terminal units for heating and ventilation.; Steam to hot water heating conversions; New Air Handling Units (AHUs) for improved heating and ventilation.; Electrical System upgrades as needed; seal the envelope of buildings to reduce heat loss

Construction Budget: $12,465,569 MM

BOE Approval Date: 12/16/22

Status: Design Phase

Anticipated Completion: 9/30/24

Storm Water Management Project

Construction Budget: $

BOE Approval Date:

Status: Design Phase

Anticipated Completion: 9/30/24