Electrical Upgrades at Meredith

 

School: William M. Meredith School

Construction Budget: $1,635,478

 

Removal of obsolete equipment (phones, speakers, TVs, etc.) and upgrade electrical power system including new circuits, panels, LED Lighting, clock system, fire alarm and data outlets.

Design Project Manager: Charles Li, P.E.
Construction Project Manager: George Leone
Project Inspector: Richard Lepore

Design Firm: FXB Engineering
Electrical Contractor: Mulhern Electric Co.

JLUY 11, 2019

Project Start

401 DAYS

Project Duration

AUGUST 15, 2020

Project Completion

$1,635,478

Construction Budget

Progress

Construction Progress: 42%

William M. Meredith School

Environmental Results