Science Lab Renovations at Penn Treaty

 

School: Penn Treaty High School

Construction Budget: $1,200,000

This project includes the renovating staff lounge 403A and classroom 404 into a Chemistry Lab with a Prep room, and renovating classroom 406 into a Biology Lab. The renovation will consist of new vinyl flooring, paint, tack and marker boards, led lighting, light switches, data and outlets, fume hoods, eye wash stations, casework and teacher and student lab work stations.

Design Project Manager: Gamil Hall
Construction Project Manager: Frank Ratka
Project Inspector: Matt McLaughlin

Design Firm: Vitteta
General Contractor: Bedwell
Mechanical Contractor: E.J. Meloney Inc.
Electrical Contractor: Madden Electrical
Plumbing Contractor: Five Star

Science lab wall demolition.
Science lab wall framing.
Science lab plaster ceiling demolition.

DECEMBER 1, 2020

Project Start

181 DAYS

Project Duration

MAY 31, 2021

Project Completion

$1,200,000

Construction Budget

Progress

Construction Progress: 20%

Penn Treaty High School

Environmental Results

1/18/21 – TEM Asbestos Analysis