Classroom Modernization at Pollock

 

School: Robert Pollock Elementary School

Construction Budget: $2,110,000

Classrooms will be fully abated and modernized with completely new finishes including floors, paint, ceilings, doors, and hardware. Electrical improvements will include new lights and receptacles.

Design Project Manager: Francis Matejik
Construction Project Manager: Ken Dickson
Project Inspector: Ben Pak

Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: TE Construction Services, LLC
Electrical Contractor: Paramount Electrical Service, LLC

Modernized classroom 101.

New floor in room 100.

New classroom furniture.

MAY 15, 2020

Project Start

168 DAYS

Project Duration

OCTOBER 30, 2020

Project Completion

$2,669,000

Construction Budget

Progress

Construction Progress: 100%

Pollock Elementary

Environmental Results

There are no environmental testing results at this time.