Site Improvement at Rowen

 

School: William Rowen Elementary School

Construction Budget: $175,000

Project includes the removal of the existing gas fired emergency generator and related panel as well as modifications to window louvers for exhaust pipe and diesel fuel tank vent piping.

Design Project Manager: Charles Li
Construction Project Manager: Joe Kehoe
Project Inspector: Wayne Howard

Design Firm: Gannett Fleming
Electrical Contractor: Madden Electric Associates

New vent and exhaust piping.
New distribution panel.
New generator.

January 23, 2020

Project Start

150 DAYS

Project Duration

June 21, 2020

Project Completion

$175,000

Construction Budget

Progress

Construction Progress: 100%

Rowen Elementary

Environmental Results

There are no environmental testing results at this time.