School: Roxborough High School
Construction Budget: $6,098,500
Construction Project Manager: Raymond Sieger
Project Inspectors: Craig Ovington
General Contractor: Aetna Roofing Corp./Weatherproofing Technologies Inc.
Masonry work on the chimney.
“Before” image of current roof.
Roof damage.
Repaired roof damage.
DECEMBER 31, 2019
Project Start
274 DAYS
Project Duration
SEPTEMBER 30, 2020
Project Completion
$6,098,500
Construction Budget