Electrical Upgrade at Stanton

 

School: E.M. Stanton Elementary School

Construction Budget: $1,996,527

 

Building will undergo a full upgrade of the electrical system including new primary electrical service, transformer, circuit panels, branch circuit wiring and devices, CAT-6 data wiring and outlets. New LED lighting and controls, including occupancy and daylight harvesting sensors will be installed. There will also be a new fire alarm system, new wireless clock system, and a new CCTV security camera system. All obsolete equipment will be removed.

Design Project Manager: Charles Li, P.E.
Construction Project Manager: George Leone
Project Inspector: Richard Lepore

Design Firm: FXB Engineering
Electrical Contractor: Hyde Electric Corp.

FEBRUARY 21, 2020

Project Start

346 DAYS

Project Duration

FEBRUARY 1, 2021

Project Completion

$1,996,527

Construction Budget

Progress

Construction Progress: 5%

E.M. Stanton

Environmental Results

There are no environmental testing results at this time.