Vare-Washington ES

Vare-Washington Elementary School

1198 S 5th St,

Philadelphia, PA 19147

Planning Phase

No projects are currently in this phase

Design Phase

No projects are currently in this phase

Construction Phase

Major Mechanical Renovation

Budget: $4,772, 053

BOE Approval  Date: 2/24/22

Scope of Work: Major mechanical renovation including replacement of the existing boilers and classroom unit ventilators, new HVAC piping, adding a new chiller plant, and replacement of the underground oil tank.

 

Project Progress

Construction Phase 0%

Complete

Classroom Modernization

Budget: $757,391

BOE Approval Date: August 6, 2021