School: John Welsh Elementary School
Construction Budget: $2,161,575
Schools will be closed for spring break March 25-28th.
All administrative offices and schools will be closed Friday, March 29th in observance of Good Friday.
We welcome students back on Monday, April 1!
Design Project Manager: Gamil Hall
Construction Project Manager: Ray Sieger
Project Inspector: Craig Ovington
Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: TE Construction Services, LLC
Electrical Contractor: Mulhern Electric Co.
MAY 21, 2020
Project Start
96 DAYS
Project Duration
AUGUST 25, 2020
Project Completion
$2,161,575
Construction Budget
There are no environmental testing results at this time.