Classroom Modernization at Welsh

 

School: John Welsh Elementary School

Construction Budget: $2,161,575

 

8 classrooms will be fully abated and modernized with completely new finishes including floors, paint, ceilings, doors, and hardware. Electrical improvements will include new lights, receptacles and controls. Entire school will also undergo a full lead-safe paint and plaster stabilization.

Design Project Manager: Gamil Hall
Construction Project Manager: Ray Sieger
Project Inspector: Craig Ovington

Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: TE Construction Services, LLC
Electrical Contractor: Mulhern Electric Co.

Modernized classroom.
Modernized and stabilized auditorium.
New sound panels in gym.

MAY 21, 2020

Project Start

96 DAYS

Project Duration

AUGUST 25, 2020

Project Completion

$2,161,575

Construction Budget

Progress

Construction Progress: 100%