School: Woodrow Wilson Middle School
Construction Budget: $11,161,426
Schools will be closed for spring break March 25-28th.
All administrative offices and schools will be closed Friday, March 29th in observance of Good Friday.
We welcome students back on Monday, April 1!
Design Firm: The Sheward Partnership
Design Project Manager: Gamil Hall
Construction Project Manager: Joe Kehoe
Project Inspector: Wayne Howard
General Contractor: BSI Construction, LLC
Mechanical Contractor: Dolan Mechanical, Inc.
Electrical Contractor: Mulhern Electric Co., Inc.
Plumbing Contractor: Herman Goldner Co., Inc.
Curved duct air filter racks and filters.
Extension rails and stabilizers.
New stage curtains.
New turf field in play yard.
New retaining wall and fencing at perimeter of school.
Typical classroom renovation.
New ceiling, lighting, and paint in hallway.
JULY 26, 2018
Project Start
798 DAYS
Project Duration
OCTOBER 1, 2020
Project Completion
$11,161,426
Construction Budget
10/22/19 – Asbestos Abatement Interim Statement of Completion