School: Camelot Academy of Philadelphia at Boone
Construction Budget: $119,000
Design Firm: NORR
Design Project Manager: Charlie Li
Construction Project Manager: Frank Ratka III
Project Inspector: Patrick McMahon
Electrical Contractor: Hyde Electric Co.
Old Transfer Switch
New conduit run.
New generator.
JANUARY 30, 2020
Project Start
153 DAYS
Project Duration
JUNE 30, 2020
Project Completion
$119,000
Construction Budget
There are no environmental testing results at this time.