School: James Dobson Elementary School
Construction Budget: $430,777
Construction Project Manager: Raymond Sieger
Project Inspector: Craig Ovington
General Contractor: Robert Michaels and Associates, Inc.
Dobson facade wall.
Exterior facade work.
JANUARY 17, 2020
Project Start
210 DAYS
Project Duration
AUGUST 14, 2020
Project Completion
$430,777
Construction Budget
There are no environmental testing results at this time.