Summer 2022 Operations Projects
As the 2021-22 school year comes to a close, the Division of Operations is gearing up for summer work to ensure all District facilities are ready for the first day of school in August!
To make this process easy to navigate, we have created a list of the schools that will be inaccessible during the summer, and this is noted with an “Access to Buildings” column. This identifies facilities where Operations work is being done that will be off-limits to school administration and the community. In some instances, “no access” will only apply to certain parts of the building, and that will be explained below. For projects that extend beyond the summer break, all construction activities have been coordinated and approved by school officials to not impact school instruction.
School | Project Type | Start Date | Completion Date | Office | Access |
---|---|---|---|---|---|
Allen, Ethan School | Major Renovation | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Allen, Ethan School | Major Renovation & Addition | 09/30/20 | 08/26/22 | Capital Programs | No access to the entire building. Major renovation work occurring in the entire school. |
Amy Levering | Ventilation Project | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Anderson, Add B. | Schoolyard Improvements | 02/07/22 | 09/30/22 | Capital Programs | No access to the schoolyard or parking lot. Access to the school building is allowed. Installing new play surface and new play equipment in the yard. |
Bethune, Mary McLeod School | GESA 2 | 06/24/22 | 10/28/22 | Capital Programs | No access to the entire building. Ductwork, piping, and major equipment underway in classrooms and public spaces. |
Brown, Joseph H. School | GESA 2 | 06/24/22 | 10/28/22 | Capital Programs | No access to the entire building. Ductwork, piping, and major equipment underway in classrooms and public spaces. |
Bryant, William C. School | Electrical Upgrade | 06/15/22 | 08/18/23 | Capital Programs | No access to the entire building. Installing conduit throughout the classrooms and corridors. |
Carnell, Laura H. School | GESA 1 | 06/24/20 | 10/29/21 | Capital Programs | No access to the entire building. Completion of the cooling and heating system. Insulation of the new piping throughout the school. |
Catherine, Joseph | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms throughout the school. |
Catherine, Joseph Annex | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the pre-K classrooms in the annex. |
Comly, Watson School | Window Replacement | 12/08/21 | 12/08/22 | Capital Programs | Access coordinated with the Project Manager and Principal. The windows will be installed in the classrooms in a stacked phasing timeline. |
Decatur, Stephen | Generator & Fire Alarm Extension | 02/10/22 | 02/10/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Extending F/A to the auxiliary buildings and emergency power circuits. |
Disston | Ventilation Caulk | 06/29/22 | 07/06/22 | Environmental | Access is available once the work is completed in full. |
Edmonds, Franklin S. School | Major HVAC Renovation | 10/12/21 | 10/01/22 | Capital Programs | No access to the entire building. Installation of new nit ventilators and renovation of the auditorium. |
Elkin, Lewis School | Major HVAC Renovation | 12/15/21 | 08/01/23 | Capital Programs | No access to the entire building. Abatement of piping and installation of new piping on 2nd floor. |
Ellwood School | Window Replacement | 06/15/22 | 08/18/23 | Capital Programs | Access coordinated with the Project Manager and Principal. The windows will be installed in the classrooms in a stacked phasing timeline. |
Emlen | Ventilation Project | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Farrell, Louis H. | Schoolyard Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the schoolyard or parking lot Installing new play surface and new play equipment in the yard. |
Fell | Ventilation Caulk | 06/22/22 | 06/28/22 | Environmental | Access is available once the work is completed in full. |
Feltonville Intermediate | Fire Alarm Replacement | 12/17/21 | 12/09/22 | Capital Programs | Access coordinated with Project Manager and Principal. Installing conduit throughout the classrooms and corridors. |
Finletter | Ventilation Caulk | 07/07/22 | 07/14/22 | Environmental | Access is available once the work is completed in full. |
Forrest, Edwin School | Major Renovation | 06/15/22 | 09/29/23 | Capital Programs | No access to the entire building. Abatement of piping throughout the school. |
Fox Chase School | Building Envelope Renovations | 12/08/21 | 01/30/23 | Capital Programs | No access to the entire building. Replacement of the windows in each classroom. The windows will be installed in the classrooms in a stacked phasing timeline. |
Frank, Anne School | Major Renovation & Addition | 06/17/20 | 09/30/22 | Capital Programs | No access to the entire building. Installation of new unit ventilators on 2nd and 3rd floor. Installlation of new ligthing and new accessible bathroom on 1st floor. Renovations to auditorium, cafeteria, schoolyard and parking lot. |
Franklin Elementary | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms throughout the school. |
Furness, Horace High School | Fire Alarm Replacement | 06/15/22 | 06/23/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Installing conduit throughout the classrooms and corridors. |
Furness, Horace High School | Lead Stabilization and Paint throughout building | 06/15/22 | 08/19/22 | Maintenance | No access to the entire building. Paint stabilization in all classrooms and hallways. |
Gideon, Edward School | Electrical Upgrade | 04/13/21 | 08/12/22 | Capital Programs | No access to the entire building. Change over of the main electrical switchgear and power system. |
Girls High (Phila HS for Girls) | Electrical Upgrade | 10/14/21 | 02/06/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Installing conduit throughout the classrooms and corridors. |
Hartranft, John F. School | Structural Repairs | 02/12/21 | 02/07/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Replacement of roofing system and masonry on the yard side elevations. |
Hopkinson, Francis School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms in the main building and auxiliary buildings. |
Houston | Ventilation Project | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Jackson | Hallways and Stairwells 3, 2, 1, Bsmt | 06/14/22 | 08/10/22 | Environmental | Access is available once the work is completed in full. |
JS Jenks | Attic, Gym,Cafeteria, Hallways, Stairwells,3,2,1 Basement | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Kearny, Gen. Philip School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms throughout the school. |
Kelley, William D. School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms throughout the school. |
Kensington Culinary | HVAC Improvements | 06/15/22 | 08/19/22 | Maintenance | No access to the entire building. HVAC Mechanical replacement in all classrooms and hallways. |
Labrum School | Fire Alarm Replacement | 11/18/21 | 11/18/22 | Capital Programs | Access coordinated with the Project Manager and Principal. Installing F/A conduit and wire throughout the classrooms and corridors. |
Lawton, Henry W. School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms in the original building and addition. |
Leeds, Hill Freeman | Major HVAC Renovation | 06/15/22 | 07/28/23 | Capital Programs | No access to the entire building. Abatement of ACPI in crawl spaces and pipe replacement in classrooms. |
Lingelbach, Anna L. | Schoolyard Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the schoolyard or parking lot. Installing new play surface and new play equipment in the yard. |
Logan,James | Toilet Room Renovation | 12/20/21 | 01/30/23 | Capital Programs | No access to the entire building. Installing ceramic tile and new fixtures in stacked student restrooms. |
Longstreth | HVAC Improvements | 06/15/22 | 08/19/22 | Maintenance | No access to the entire building. HVAC Mechanical replacement and duct cleaning in all classrooms and hallways. |
Lowell, James R. School | GESA 1.3 | 03/01/22 | 12/31/23 | Capital Programs | No access to the entire building. Abatement of ACPI in the attic. Installation of new piping and unit ventilators in classrooms. |
Ludlow, James R Annex (Comm.Ctr) | Roof Replacement | 06/15/22 | 01/27/23 | Capital Programs | No access to the entire building. Replacement of the roofing system. |
Marshall, John School | Door Replacement | 12/02/21 | 12/02/22 | Capital Programs | Access coordinated with the Project Manager and Principal. Replacement and refinishing of the classroom doors and hardware throughout the school. |
Mayfair School | Classroom Addition | 01/03/22 | 01/27/23 | Capital Programs | No access SDP renovation of existing building and new addition. |
McDaniel, Delaplaine School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms throughout the school. |
McMichael, Morton | Site Improvements | 06/15/22 | 08/12/22 | Capital Programs | No access to the schoolyard or parking lot. Installing new play surface and new play equipment in the yard. |
Meade, Gen. George G. School | Roof Replacement | 06/21/21 | 06/21/22 | Capital Programs | No access to the top floor. Yard access is restricted. Installation of the new coping metal throughout the building. |
Meehan, Austin | Roof and Major HVAC Renovation | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Replacement of the classroom unit ventilators throughout the building and moving different school programs around the school. |
Mifflin | Attic | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring in the attic. |
Mitchell | Ventilation Caulk | 06/14/22 | 06/21/22 | Environmental | Access is available once the work is completed in full. |
Morris, Robert School | Structural Repairs | 06/15/22 | 04/28/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Repairs of the facade and brick replacement on yard elevations. |
Morton, Thomas G School | Major HVAC Renovation | 01/20/21 | 06/24/22 | Capital Programs | No access to the entire building. Start up and balancing of the HVAC system and installing new pipe insulation throughout the school. |
Northeast Community Propel Academy | Warranty item: Flooring Replacement at all common areas/hallways | 06/15/22 | 08/06/22 | Capital Programs | Access to administration area only. Replacement of floor covering in corridors and classrooms. |
Parkway CC | Ventilation/ IT project | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Parkway-Northwest High School | Science Lab Modernization | 06/15/22 | 02/24/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Abatement and demolition activities in the classrooms scheduled for renovation. |
Patterson, John M. School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms in the main building and auxiliary building. |
Penn Treaty | Lead Stabilization and Paint throughout building B-4 only | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. |
Pennell, Joseph Elementary | Schoolyard Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the schoolyard or parking lot. Installing new play surface and new play equipment in the yard. |
Pennypacker, Samuel School | Relighting Project | 11/18/21 | 11/18/22 | Capital Programs | Access coordinated with the Project Manager and Principal. Replacement of the light fixtures in office suite, gym, lunch room and classrooms. |
Pollock, Robert B. School | Addition and Major Renovations | 06/15/22 | 07/28/23 | Capital Programs | No access to the entire building. Major renovation through school, including abatement. |
Potter-Thomas School | Mechanical Plant Replacement | 06/15/22 | 07/28/23 | Capital Programs | Access coordinated with the Project Manager and Principal. Abatement of ACPI piping throughout the school. |
Rhawnhurst School | Major Addition and Renovation | 06/15/22 | 03/31/24 | Capital Programs | No access to the entire building. Major renovation thourghout existing school and new addition. |
Richmond School | Major Addition and Renovation | 03/02/20 | 08/21/22 | Capital Programs | No access to the entire building. Completion of gym floor and preparation for ribbon cutting. |
SLA@Beeber | GESA 2 | 06/24/22 | 10/28/22 | Capital Programs | No access to the entire building. Installing new classroom ventilation equipment and piping starting on the 3rd floor working down. |
Spring Garden School | Building Envelope Renovation | 06/15/22 | 07/28/23 | Capital Programs | Access coordinated with the Project Manager and Principal. |
Steel | HVAC Improvements | 06/15/22 | 08/19/22 | Maintenance | No access to the entire building. HVAC Mechanical replacement and duct cleaning in all classrooms and hallways. |
Sullivan, James J. School | Building Envelope Renovation | 11/18/21 | 12/30/22 | Capital Programs | No access to the entire building. Window replacement in classrooms throughout the building in a stacked phasing timeline. |
Taylor, Bayard School | Roof Replacement | 06/15/22 | 06/23/23 | Capital Programs | No access to the top floor. Yard access is restricted. Demolition and replacement of the roofing. |
Vare-Washington Elementary | Major HVAC Renovation | 04/15/22 | 10/27/23 | Capital Programs | No access to the entire building. Abatement of the attic space, replacement of unit ventilator and piping throughout the school. |
Wagner | Hallways and Stairwells, Cafeterias, 3,2,1, Auditorium,Fan Rooms (2) | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. Environmental work occurring throughout the building. |
Waring, Laura W. School | Electrical Service Upgrades | 06/15/22 | 06/23/23 | Capital Programs | No access to the entire building. Conduit installation in corridors and areas normally occupied by students. |
Washington, Martha School | Classroom Improvements | 06/15/22 | 10/28/22 | Capital Programs | No access to the entire building. Renovation of the K-3 classrooms throughout the school. |
Welsh | Crawl Space/ventilation | 06/14/22 | 08/05/22 | Environmental | No access to the entire building. |
Wright, Richard R. School | Mechanical Plant Replacement | 06/15/22 | 10/27/23 | Capital Programs | No access to the entire building. Abatement of ACPI piping throughout the school. |