Summer 2022 Operations Projects

As the 2021-22 school year comes to a close, the Division of Operations is gearing up for summer work to ensure all District facilities are ready for the first day of school in August!

To make this process easy to navigate, we have created a list of the schools that will be inaccessible during the summer, and this is noted with an “Access to Buildings” column. This identifies facilities where Operations work is being done that will be off-limits to school administration and the community. In some instances, “no access” will only apply to certain parts of the building, and that will be explained below. For projects that extend beyond the summer break, all construction activities have been coordinated and approved by school officials to not impact school instruction.

SchoolProject TypeStart DateCompletion DateOfficeAccess
Allen, Ethan SchoolMajor Renovation06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
Allen, Ethan SchoolMajor Renovation & Addition09/30/2008/26/22Capital ProgramsNo access to the entire building. Major renovation work occurring in the entire school.
Amy LeveringVentilation Project06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
Anderson, Add B.Schoolyard Improvements02/07/2209/30/22Capital ProgramsNo access to the schoolyard or parking lot. Access to the school building is allowed. Installing new play surface and new play equipment in the yard.
Bethune, Mary McLeod SchoolGESA 206/24/2210/28/22Capital ProgramsNo access to the entire building. Ductwork, piping, and major equipment underway in classrooms and public spaces.
Brown, Joseph H. SchoolGESA 206/24/2210/28/22Capital ProgramsNo access to the entire building. Ductwork, piping, and major equipment underway in classrooms and public spaces.
Bryant, William C. SchoolElectrical Upgrade06/15/2208/18/23Capital ProgramsNo access to the entire building. Installing conduit throughout the classrooms and corridors.
Carnell, Laura H. SchoolGESA 106/24/2010/29/21Capital ProgramsNo access to the entire building. Completion of the cooling and heating system. Insulation of the new piping throughout the school.
Catherine, JosephClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms throughout the school.
Catherine, Joseph AnnexClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the pre-K classrooms in the annex.
Comly, Watson SchoolWindow Replacement12/08/2112/08/22Capital ProgramsAccess coordinated with the Project Manager and Principal. The windows will be installed in the classrooms in a stacked phasing timeline.
Decatur, StephenGenerator & Fire Alarm Extension02/10/2202/10/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Extending F/A to the auxiliary buildings and emergency power circuits.
DisstonVentilation Caulk06/29/2207/06/22EnvironmentalAccess is available once the work is completed in full.
Edmonds, Franklin S. SchoolMajor HVAC Renovation10/12/2110/01/22Capital ProgramsNo access to the entire building. Installation of new nit ventilators and renovation of the auditorium.
Elkin, Lewis SchoolMajor HVAC Renovation12/15/2108/01/23Capital ProgramsNo access to the entire building. Abatement of piping and installation of new piping on 2nd floor.
Ellwood SchoolWindow Replacement06/15/2208/18/23Capital ProgramsAccess coordinated with the Project Manager and Principal. The windows will be installed in the classrooms in a stacked phasing timeline.
EmlenVentilation Project06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
Farrell, Louis H.Schoolyard Improvements06/15/2210/28/22Capital ProgramsNo access to the schoolyard or parking lot Installing new play surface and new play equipment in the yard.
FellVentilation Caulk06/22/2206/28/22EnvironmentalAccess is available once the work is completed in full.
Feltonville IntermediateFire Alarm Replacement12/17/2112/09/22Capital ProgramsAccess coordinated with Project Manager and Principal. Installing conduit throughout the classrooms and corridors.
FinletterVentilation Caulk07/07/2207/14/22EnvironmentalAccess is available once the work is completed in full.
Forrest, Edwin SchoolMajor Renovation06/15/2209/29/23Capital ProgramsNo access to the entire building. Abatement of piping throughout the school.
Fox Chase SchoolBuilding Envelope Renovations12/08/2101/30/23Capital ProgramsNo access to the entire building. Replacement of the windows in each classroom. The windows will be installed in the classrooms in a stacked phasing timeline.
Frank, Anne SchoolMajor Renovation & Addition06/17/2009/30/22Capital ProgramsNo access to the entire building. Installation of new unit ventilators on 2nd and 3rd floor. Installlation of new ligthing and new accessible bathroom on 1st floor. Renovations to auditorium, cafeteria, schoolyard and parking lot.
Franklin ElementaryClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms throughout the school.
Furness, Horace High SchoolFire Alarm Replacement06/15/2206/23/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Installing conduit throughout the classrooms and corridors.
Furness, Horace High SchoolLead Stabilization and Paint throughout building06/15/2208/19/22MaintenanceNo access to the entire building. Paint stabilization in all classrooms and hallways.
Gideon, Edward SchoolElectrical Upgrade04/13/2108/12/22Capital ProgramsNo access to the entire building. Change over of the main electrical switchgear and power system.
Girls High (Phila HS for Girls)Electrical Upgrade10/14/2102/06/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Installing conduit throughout the classrooms and corridors.
Hartranft, John F. SchoolStructural Repairs02/12/2102/07/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Replacement of roofing system and masonry on the yard side elevations.
Hopkinson, Francis SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms in the main building and auxiliary buildings.
HoustonVentilation Project06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
JacksonHallways and Stairwells 3, 2, 1, Bsmt06/14/2208/10/22EnvironmentalAccess is available once the work is completed in full.
JS JenksAttic, Gym,Cafeteria, Hallways, Stairwells,3,2,1 Basement06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
Kearny, Gen. Philip SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms throughout the school.
Kelley, William D. SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms throughout the school.
Kensington CulinaryHVAC Improvements06/15/2208/19/22MaintenanceNo access to the entire building. HVAC Mechanical replacement in all classrooms and hallways.
Labrum SchoolFire Alarm Replacement11/18/2111/18/22Capital ProgramsAccess coordinated with the Project Manager and Principal. Installing F/A conduit and wire throughout the classrooms and corridors.
Lawton, Henry W. SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms in the original building and addition.
Leeds, Hill FreemanMajor HVAC Renovation06/15/2207/28/23Capital ProgramsNo access to the entire building. Abatement of ACPI in crawl spaces and pipe replacement in classrooms.
Lingelbach, Anna L.Schoolyard Improvements06/15/2210/28/22Capital ProgramsNo access to the schoolyard or parking lot. Installing new play surface and new play equipment in the yard.
Logan,JamesToilet Room Renovation12/20/2101/30/23Capital ProgramsNo access to the entire building. Installing ceramic tile and new fixtures in stacked student restrooms.
LongstrethHVAC Improvements06/15/2208/19/22MaintenanceNo access to the entire building. HVAC Mechanical replacement and duct cleaning in all classrooms and hallways.
Lowell, James R. SchoolGESA 1.303/01/2212/31/23Capital ProgramsNo access to the entire building. Abatement of ACPI in the attic. Installation of new piping and unit ventilators in classrooms.
Ludlow, James R Annex (Comm.Ctr)Roof Replacement06/15/2201/27/23Capital ProgramsNo access to the entire building. Replacement of the roofing system.
Marshall, John SchoolDoor Replacement12/02/2112/02/22Capital ProgramsAccess coordinated with the Project Manager and Principal. Replacement and refinishing of the classroom doors and hardware throughout the school.
Mayfair SchoolClassroom Addition01/03/2201/27/23Capital ProgramsNo access SDP renovation of existing building and new addition.
McDaniel, Delaplaine SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms throughout the school.
McMichael, MortonSite Improvements06/15/2208/12/22Capital ProgramsNo access to the schoolyard or parking lot. Installing new play surface and new play equipment in the yard.
Meade, Gen. George G. SchoolRoof Replacement06/21/2106/21/22Capital ProgramsNo access to the top floor. Yard access is restricted. Installation of the new coping metal throughout the building.
Meehan, AustinRoof and Major HVAC Renovation06/15/2210/28/22Capital ProgramsNo access to the entire building. Replacement of the classroom unit ventilators throughout the building and moving different school programs around the school.
MifflinAttic06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring in the attic.
MitchellVentilation Caulk06/14/2206/21/22EnvironmentalAccess is available once the work is completed in full.
Morris, Robert SchoolStructural Repairs06/15/2204/28/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Repairs of the facade and brick replacement on yard elevations.
Morton, Thomas G SchoolMajor HVAC Renovation01/20/2106/24/22Capital ProgramsNo access to the entire building. Start up and balancing of the HVAC system and installing new pipe insulation throughout the school.
Northeast Community Propel AcademyWarranty item: Flooring Replacement at all common areas/hallways06/15/2208/06/22Capital ProgramsAccess to administration area only. Replacement of floor covering in corridors and classrooms.
Parkway CCVentilation/ IT project06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
Parkway-Northwest High SchoolScience Lab Modernization06/15/2202/24/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Abatement and demolition activities in the classrooms scheduled for renovation.
Patterson, John M. SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms in the main building and auxiliary building.
Penn TreatyLead Stabilization and Paint throughout building B-4 only06/14/2208/05/22EnvironmentalNo access to the entire building.
Pennell, Joseph ElementarySchoolyard Improvements06/15/2210/28/22Capital ProgramsNo access to the schoolyard or parking lot. Installing new play surface and new play equipment in the yard.
Pennypacker, Samuel SchoolRelighting Project11/18/2111/18/22Capital ProgramsAccess coordinated with the Project Manager and Principal. Replacement of the light fixtures in office suite, gym, lunch room and classrooms.
Pollock, Robert B. SchoolAddition and Major Renovations06/15/2207/28/23Capital ProgramsNo access to the entire building. Major renovation through school, including abatement.
Potter-Thomas SchoolMechanical Plant Replacement06/15/2207/28/23Capital ProgramsAccess coordinated with the Project Manager and Principal. Abatement of ACPI piping throughout the school.
Rhawnhurst SchoolMajor Addition and Renovation06/15/2203/31/24Capital ProgramsNo access to the entire building. Major renovation thourghout existing school and new addition.
Richmond SchoolMajor Addition and Renovation03/02/2008/21/22Capital ProgramsNo access to the entire building. Completion of gym floor and preparation for ribbon cutting.
SLA@BeeberGESA 206/24/2210/28/22Capital ProgramsNo access to the entire building. Installing new classroom ventilation equipment and piping starting on the 3rd floor working down.
Spring Garden SchoolBuilding Envelope Renovation06/15/2207/28/23Capital ProgramsAccess coordinated with the Project Manager and Principal.
SteelHVAC Improvements06/15/2208/19/22MaintenanceNo access to the entire building. HVAC Mechanical replacement and duct cleaning in all classrooms and hallways.
Sullivan, James J. SchoolBuilding Envelope Renovation11/18/2112/30/22Capital ProgramsNo access to the entire building. Window replacement in classrooms throughout the building in a stacked phasing timeline.
Taylor, Bayard SchoolRoof Replacement06/15/2206/23/23Capital ProgramsNo access to the top floor. Yard access is restricted. Demolition and replacement of the roofing.
Vare-Washington ElementaryMajor HVAC Renovation04/15/2210/27/23Capital ProgramsNo access to the entire building. Abatement of the attic space, replacement of unit ventilator and piping throughout the school.
WagnerHallways and Stairwells, Cafeterias, 3,2,1, Auditorium,Fan Rooms (2)06/14/2208/05/22EnvironmentalNo access to the entire building. Environmental work occurring throughout the building.
Waring, Laura W. SchoolElectrical Service Upgrades06/15/2206/23/23Capital ProgramsNo access to the entire building. Conduit installation in corridors and areas normally occupied by students.
Washington, Martha SchoolClassroom Improvements06/15/2210/28/22Capital ProgramsNo access to the entire building. Renovation of the K-3 classrooms throughout the school.
WelshCrawl Space/ventilation06/14/2208/05/22EnvironmentalNo access to the entire building.
Wright, Richard R. SchoolMechanical Plant Replacement06/15/2210/27/23Capital ProgramsNo access to the entire building. Abatement of ACPI piping throughout the school.