Site Improvements at Central
Construction Budget: $6,399,500
The entire site is being excavated to install a new parking lot, stormwater piping and inlets, utilities, new exterior and parking area lighting, exterior classrooms and removal of coal tunnel that is no longer in service. New driveways and a loading dock area will also be added. This is Phase One(1) of a Two(2) Phase project to prepare for an upcoming Performing Arts Center on the same site.
Construction Project Manager: Raymond Sieger
Project Inspector: Craig Ovington
General Contractor: Bencardino Excavating Inc.
Plumbing Contractor: Paramount Electric LLC
APRIL 22, 2019
Project Start
549 DAYS
Project Duration
OCTOBER 22, 2021
Project Completion
$6,399,500
Construction Budget
Progress
Construction Progress: 100%
Environmental Results
There are no environmental testing results at this time.
Last modified: October 8, 2020