Cayuga

School: Cayuga Elementary School

Construction Budget: $1,615,900

 

Kindergarten thru third grade classrooms are being modernized with all new finishes, including floors, paint, ceilings, doors and hardware. Electrical improvements will include new lights and receptacles.

Design Firm: Crabtree, Rohrbaugh & Associates
Design Project Manager: Amy Hunnicut
Construction Project Manager: Joe Kehoe
Project Inspector: Wayne Howard

General Contractor: Magnum, Inc.
Electrical Contractor: Mulhern Electric Co., Inc.

Classroom 206.
Classroom 120 setup.
New Smartboard.

Progress

Construction Progress: 100100

May 1, 2020

Project Start

182 DAYS

Project Duration

October 30, 2020

Project Completion

$1,615,900

Project Budget

Cayuga Elementary School

Environmental Results

There are no environmental testing results at this time.