Chester A. Arthur School

Chester A. Arthur School

2000 Catharine St
Philadelphia, Pa 19146

Planning Phase

No projects are currently in this phase

Design Phase

Electrical Upgrades

Budget: $3,312,000

Status: Pending Bid Process

Board Approval: TBD

Scope of Work: Replacement of electrical infrastructure; installation of window air conditioners throughout; relighting, fire alarm replacement, installation of security cameras, and all electrical services.

Project Planning & Design focuses on the schematic design phase of a project. In this phase, we assess academic program requirements, review the existing layout, create new building designs, review building codes and regulations, coordinate schematics with consultants,  communicate design concepts with stakeholders, and prepare the cost of work estimates.

Construction Phase

No projects are currently in this phase

Complete

No projects are currently in this phase