Classroom Modernization at Ellwood

 

School: Ellwood Elementary School

Construction Budget: $1,521,000

 

Kindergarten thru 3rd grade classrooms are being modernized with all new finishes, including floors, paint, ceilings, doors and hardware. Electrical improvements will include new lights and receptacles.

Design Project Manager: Francis Matejik
Construction Project Manager: Joe Kehoe
Project Inspector: Wayne Howard

Design Firm: Crabtree, Rohrbaugh & Associates
General Contractor: TE Construction Services
Electrical Contractor: Paramount Electrical Services

MAY 1, 2020

Project Start

162 DAYS

Project Duration

OCTOBER 30, 2020

Project Completion

$1,521,000

Construction Budget

Progress

Construction Progress: 10%