Classroom Modernization at J. Marshall

 

School: John Marshall Elementary School

Construction Budget: $2,617,175

11 classrooms will be fully abated and modernized with completely new finishes including floors, paint, ceilings, doors, and hardware. Electrical improvements will include new lights and receptacles. Building will also undergo full paint and plaster stabilization.

Design Project Manager: Amy Hunnicut
Construction Project Manager: Frank Ratka III
Project Inspector: Patrick McMahon

Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: Lorenzon Brothers
Electrical Contractor: Paramount Electrical Service, LLC

Upgraded bathroom.

New classroom cubbies.

Freshly painted learning wall.

MAY 1, 2020

Project Start

116 DAYS

Project Duration

AUGUST 25, 2020

Project Completion

$2,617,175

Construction Budget

Progress

Construction Progress: 100%

J. Marshall Elementary

Environmental Results

There are no environmental testing results at this time.