Overbrook Education Center

 

School: Overbrook Educational School

Construction Budget: $1,391,200

 

8 classrooms will be fully abated and modernized with completely new finishes including floors, paint, ceilings, doors, and hardware. Electrical improvements will include new lights and receptacles. Entire school will also undergo a full lead-safe paint and plaster stabilization.

Design Project Manager: Amy Hunnicut
Construction Project Manager: Kevin Courtney
Project Inspector: Trever Alfonso

Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: Lorenzon Brothers Company
Electrical Contractor: Paramount Electrical Services

MAY 11, 2020

Project Start

172 DAYS

Project Duration

OCTOBER 30, 2020

Project Completion

$1,391,200

Construction Budget

Progress

Construction Progress: 100100%