School: Overbrook Educational School
Construction Budget: $1,391,200
Design Project Manager: Amy Hunnicut
Construction Project Manager: Kevin Courtney
Project Inspector: Trever Alfonso
Design Firm: Crabtree, Rohrbaugh, and Associates
General Contractor: Lorenzon Brothers Company
Electrical Contractor: Paramount Electrical Services
MAY 11, 2020
Project Start
172 DAYS
Project Duration
OCTOBER 30, 2020
Project Completion
$1,391,200
Construction Budget
There are no environmental testing results at this time.