Major Renovation at James Rhoads

School: James Rhoads School
Construction Budget: $8,681,540

Design Firm: Godshall, Kane and O’Rourke Architects, LLC
General Contractor: Smith Construction Inc.
Mechanical Contractor: All States Mechanical
Electrical Contractor: Madden Electric
Plumbing Contractor: Chadwick Services

Design Project Manager: Jeff Gilbeaux
Construction Project Manager: Mario Tamborello
Project Inspector: Tom McGahan

Scope of Work: The project includes: the comprehensive replacement of elevator, windows, boilers, and HVAC systems.

Progress

Construction Progress: 55%