Site Improvement at Sayre

 

School: William Sayre High School

Construction Budget: $4,002,000

Project includes removal of four underground oil storage tanks and replacement with one new tank; removal of existing steam boiler plant and replacement with new plant; upgraded power for new plant and brand new lighting in boiler room.

Design Project Manager: Jeffrey Gilbeaux
Construction Project Manager: Kevin Courtney
Project Inspector: Trever Alfonso

Design Firm: Gannett Fleming
Mechanical Contractor: GEM Mechanical Services, Inc.
Electrical Contractor: C.A.D. Electric, Inc.
General Contractor: Murphy, Quigley Company, Inc.

Abatement containment in Gymnasium.
Dig work for tanks.
Temporary fence in Back lot.
New boilers, burners, pipes and insulation.
Caution fence in boiler room.
Utility fan conduit rack.

Progress

Construction Progress: 67%

June 12, 2020

Project Start

186 DAYS

Project Duration

December 15, 2020

Project Completion

$4,002,000

Construction Budget

Sayre High School

Environmental Results

9/24/20 – Certificate of PLM Analysis