School: Swenson Arts & Technology High School
Construction Budget: $1,971,100
Design Firm: BWA
Design Project Manager: Francis Matejik
Construction Project Manager: Ken Dickson
Project Inspector: Ben Pak
General Contractor: TE Construction Services, LLC
Mechanical Contractor: PT Mechanical
Electrical Contractor: Madden Electric
SEPTEMBER 4, 2019
Project Start
397 DAYS
Project Duration
OCTOBER 4, 2020
Project Completion
$1,971,100
Construction Budget