School: Motivation High School
Construction Budget: $15,288,000
On May 9th at 4 p.m. the Board of Education will hold a Special Action Meeting. Find materials here here.
Design Firm: Schrader Group Architecture, LLC
Design Project Manager: Nicole Ward
Construction Project Manager: Kevin Courtney
Project Inspector: Trever Alfonso
General Contractor: Smith Construction
Mechanical Contractor: Allstates Mechanical, Ltd.
Electrical Contractor: Hyde Electric Corporation
Plumbing Contractor: Dolan Mechanical, Inc.
Retention basin at the rear of the school. Erosion control and silt fencing remains to help stabilize the basin.
Demolition underway of a classroom in phase C5.
Demolition underway of the hallway in phase C5.
New main entrance and gate is complete.
JUNE 25, 2018
Project Start
829 DAYS
Project Duration
OCTOBER 1, 2020
Project Completion
$15,288,000
Construction Budget
11/11/19 – Asbestos testing scheduled for today.
11/08/19 – Abatement operations in phase are to be completed today.